Application for Approval to construct on site – Building Permit 

In compliance with  Fiji  Building Code, Town Planning Act, Environment Management Act, Public Health Act, OHS Act, Subdivision By-Laws as well as requirements by the Fiji Road Authority , National Fire Authority , Water Authority of Fiji. (where required), all major development applications must be submitted to the City Council. 

This is the last step before any building is permitted to be built on the land. Once the building permit is approved, the owner can then work with the developers and engineers to commence construction. 

Service Availability

0800 - 1630H [Mon - Thurs]

0800 - 1600H [Fri]

Excluding weekends & public holidays

Service Turnaround Time

5 working days subject to complete submission of documents and compliance requirements are met. Complex developments may require more time. 

Required Forms

Checklist

Supporting Documents

All requirements specified in the checklist

Service Fee

Calculated based on the value of works

Contact Person

SCC Enquiry Counter

Email: customerservices@scc.org.fj

Tel: +679 3313433 Ext 305/306

MCTTT Logo.png
digitalfiji_transparent.jpg

Ministry of Commerce, Trade, Tourism and Transport

Level 2 and 3, Civic Tower, Victoria Parade, Suva

Tel: +679-3305411

www.mcttt.gov.fj

Copyright  2020 Ministry of Commerce, Trade, Tourism and Transport