Processing of Environmental Impact Assessments (EIAs)

In compliance with Environment Management Act 2005 and the EIA Regulations 2007, all development proposals with the potential for environmental impacts are to be submitted to the Department of Environment for review and approval. 

slantbar.jpg

Service Availability

0800 - 1630H [Mon - Thurs]

0800 - 1600H [Fri]

Excluding weekends & public holidays

slantbar.jpg

Service Turnaround Time

- 14 working days: EIA Screening Application and Determination
- 30 days: Scoping exercise and preparation of Terms of Reference
- 28 days: EIA Review upon submission of EIA report
- 7 working days: EIA decision
- 7 working days: Notification of EIA Decision to Customer

slantbar.jpg

Required Forms

slantbar.jpg

Checklist

- EIA Processing Application Checklist
- EIA Screening Application Checklist

slantbar.jpg

Supporting Documents

- Locality plan

- Lease/title

- Foreign investment certificate (if applicable)

- Concept Development Plan

slantbar.jpg

Service Fee

Fees schedule is outlined in Schedule 2 of the Environment Management (EIA Process) Regulations 2007